Air Cooled Condensor Cold Weather InstallationsSTATION OWNER (A/E) | SIZE [Mw(e)] (1) | STEAM FLOW [Lb/Hr] | TURBINE BP [IN HgA] | DESIGN TEMP. [° F]43 | YEAR | MIN °f | REMARKS | Neil Simpson I Station Black Hills Power & Light Co. Gillette , WY (Stearns Roger) | 20 | 167,550 | 4.5 | 75 | 1968 | -40 | Coal Fired Plant | Wyodak Station Black Hills Power & Light Co. and Pacific Power & Light Co. Gillette , WY (Stone & Webster) | 330 | 1,884,800 | 6.0 | 66 | 1977 | -40 | Coal Fired Plant | Beluga Unit No. 8 Chugach Electric Assoc., Inc. Beluga, AK (Burns & Roe) | 65 | 478,400 | 5.6 | 35 | 1979 | -30 | Combined Cycle | North Branch Power Station
Energy America Southeast North Branch, WV (Fru-Con Construction Corp.) | 80 | 622,000 | 7.0 | 90 | 1989 | -40 | Coal Fired Plant | Spokane Resource Rec. Facility Wheelabrator Spokane Inc. Spokane , WA (Clark-Kenith Inc.) | 26 | 153,950 | 2.0 | 47 | 1989 | -10 | WTE (Supplied & Erected) | Peel Energy From Waste Peel Resources Recovery, Inc. Brampton, Ontario, Canada (SNC Services, Ltd.) | 10 | 88,750 | 4.5 | 68 | 1990 | -20 | WTE | Nipigon Power Plant Transcanada Pipelines Nipigon, Ontario, Canada (SNC Services, Ltd.) | 15 | 169,000 | 3.0 | 59 | 1990 | -35 | Combined Cycle | University of Alaska University of Alaska, Fairbanks Fairbanks, AK | 10 | 46,000 | 6.0 | 82 | 1991 | -60 | Combined Cycle | Neil Simpson II Station Black Hills Power & Light Co. Gillette, WY (Black & Veatch) | 80 | 548,200 | 6.0 | 66 | 1992 | -40 | Coal Fired Plant | Potter Station Potter Station Power Limited
Potter, Ontario (Monenco/Bluebird) | 20 | 181,880 | 3.8 | 66 | 1993 | -40 | Combined Cycle | Streeter Generating Station Municipal Electric Utility City of Cedar Falls , Iowa
Cedar Falls , Iowa ( Stanley Consultants) | 40 | 246,000 | 3.5 | 50 | 1993 | -20 | PAC SYSTEM (Supplied & Erected) | North Bay Plant
Transcanada Pipelines North Bay , Ontario , Canada | 30 | 245,000 | 2.0 | 53.6 | 1994 | -30 | Combined Cycle | Kapuskasing Plant
Transcanada Pipelines Kapuskasing , Ontario , Canada | 30 | 245,000 | 2.0 | 53.6 | 1994 | -40 | Combined Cycle | Arbor Hills Landfill Gas Facility Browning-Ferris Gas Services Inc.
Northville , MI (European Gas Turbines Inc.) | 9 | 87,390 | 3.0 | 50 | 1994 | -20 | Combined Cycle | Pine Bend Landfill Gas Facility Browning-Ferris Gas Services Inc.
Eden Prairie , MN (European Gas Turbines Inc.) | 6 | 58,260 | 3.0 | 50 | 1994 | -40 | Combined Cycle | Mallard Lake Landfill Gas Facility Browning-Ferris Gas Services Inc.
Hanover Park , IL (Bibb & Associates Inc.) | 9 | 101,400 | 3.0 | 49 | 1996 | -20 | Combined Cycle | Dighton Power Project Dighton Power Associates, Ltd .
Dighton , MA (Parsons Power Group, Inc.) | 60 | 442,141 | 5.5 | 90 | 1997 | -10 | Combined Cycle (Supplied & Erected) | Tiverton Power Project Tiverton Power Associates, Ltd. Tiverton , RI (Stone & Webster Engineering Corp.) | 80 | 549,999 | 5.0 | 90 | 1998 | -12 | Combined Cycle | Rumford Power Project Rumford Power Associates, Ltd.
Rumford , ME (Stone & Webster Engineering Corp) | 80 | 545,800 | 5.0 | 90 | 1998 | -39 | Combined Cycle | University of Alberta
Edmonton , Alberta , Canada (Sandwell) | 25 | 277,780 | 9.15 | 59 | 1999 | -45 | Gas Fired Cogeneration | Front Range Power Project Front Range Power Company Fountain, Colorado (TIC/UE Front Range JV) | 150 | 1,266,477 | 3.57 | 80 | 2000 | -30 | Combine Cycle | Goldendale Energy Project Goldendale Energy Inc.
Goldendale , Washington (NEPCO) | 110 | 678,000 | 4.5 | 90 | 2000 | -10 | Combine Cycle PAC SYSTEM Ò | Athens Power Station PG & E Generating
Athens , New York (Bechtel Power) | 3 x 120 | 3 x 749,183 | 5 | 90 | 2000 | -28 | Combined Cycle (Supplied & Erected) | Wygen 1, Unit 3 Power Project Black Hills Generation, Inc.
Gillette , Wyoming (Babcock & Wilcox) | 80 | 548,200 | 6.0 | 66 | 2001 | -48 | Coal Fired Plant | Hunterstown Power Project Reliant Energy Hunterstown, Pennsylvania (Black & Veatch) | 350 | 1,690,000 | 4.6 | 90 | 2001 | -10 | Combined Cycle (890 MW Total) |
|
|
|
|